At its 5th meeting (November 2013, Shanghai, China), the HSSC considered a draft "Master Plan for the development and implementation of S-100". At its 7th meeting (November 2015, Busan, Republic of Korea), the HSSC endorsed Edition 1.1 - June 2015. The S-100 Master Plan is a living document which is reviewed annually by the S-100 Working Group. |
||
|
||
|
|
|
|
|
|
|
Notification to HSSC10 of a new edition of S-100 | |
Early 2019 | Publication of next edition of S-100 | Edition 4.0.0 (proposals for extensions) |
March/April 2020 | Final Consideration of proposal for next edition | |
May 2020 | Notification to HSSC12 of a new edition of S-100 | |
|
|
|
Proposals for Clarifications, Corrections and Extensions to the S-100 Standard document should be submitted to the S-100 Working Group using the maintenance procedure document. |
_______________________________________________________________________________________________________________________
The intention of the roadmap document is to provide an estimated timescale and sequence of events for the development, testing and implementation of the S-101 ENC Product Specification.
The sequence of activities is supported by a more detailed account of the various processes and impacts which are anticipated to have an effect on the various stakeholders.
At its 4th meeting (25-28 September 2012, Taunton, United Kingdom), the HSSC tasked TSMAD to add an additional work item to its work plan to produce a roadmap, taking into account the
S-101 impact study and showing key tasks that have to be completed in order to implement S-101. The current draft of the S-101 Value Added Roadmap
(April 2016) can be downloaded